A review of the performance of the Gary Energy Corporation micellar-polymer pilot in the Bell Creek Field has been completed. The ultimate recovery beyond waterflooding is projected to be 27,000 barrels of oil, compared to an anticipated level of 90,000 barrels from simulation studies. The projected incremental recovery is subject to uncertainties since significant secondary oil was being produced at the initiation of chemical injection. The predicted recover from simulation studies is considered to be optimistic, principally because the displaceable oil saturations were assumed too high. Although the anticipated recovery may have been optimistic, it is clear that the level of increased oil recovery has been disappointing and that the economics of a project if expanded would be unfavorable.

Followers: 0

Citation (Click to Copy)

Data and Resources

    Gathering Resources...

Keywords

Additional Info

Field Value
Last Updated September 29, 2016, 14:42 (LMT)
Created September 29, 2016, 14:42 (LMT)
Citation John R. Fanchi Dwight L. Dauben Herbert B. Carrol ---- Roy Long, An Evaluation of the Bell Creek Field Micellar- Polymer Pilot, 2016-09-29, https://edx.netl.doe.gov/dataset/an-evaluation-of-the-bell-creek-field-micellar-polymer-pilot
Netl Product yes
Poc Email Roy.long@netl.doe.gov
Point Of Contact Roy Long
Program Or Project KMD