Occidental vertical modified in situ process for the recovery of oil from oil shale. Phase II. Quarterly progress report, September 1-November 30, 1979

License(s):

Other (Open)

The major activities at OOSI's Logan Wash site during the quarter were: driving the access drifts towards the underground locations for Retorts 7 and 8; manway raise boring; constructing the change house; rubbling the first lift of Mini-Retort (MR)1; preparing the Mini-Retorts for tracer testing; coring of Retort 3E; and beginning the DOE instrumentation program.

Followers: 0

Citation (Click to Copy)

Data and Resources

    Gathering Resources...

Keywords

Additional Info

Field Value
Last Updated September 29, 2016, 18:41 (LMT)
Created September 29, 2016, 18:41 (LMT)
Citation Roy Long, Occidental vertical modified in situ process for the recovery of oil from oil shale. Phase II. Quarterly progress report, September 1-November 30, 1979, 2016-09-29, https://edx.netl.doe.gov/dataset/occidental-vertical-modified-in-situ-process-for-the-recovery-of-oil-from-oil-shale-phase-ii-quar1
Netl Product yes
Poc Email Roy.long@netl.doe.gov
Point Of Contact Roy Long
Program Or Project KMD
Publication Date 1979-12-1