"In Accordance with the requirements of our Contract #EF-77-C-03-1723, our quarterly report for the period August 1, 1977 to October 31, 1977 follows: As of this reporting period we have executed our lease agreement with Rocky Mountain Energy Company and surveyed the property as described in Figure 1. The Environmental Research Plan included in this report by reference has been approved and is being implemented. A Preoperational Environmental Impact Assessment has been completed and will be submitted for approval within one week. Details are presented later in this report. Our subcontract with Systems, Science and Software has been approved and effort under that contract initiated. We have not received approval of our subcontract with Science Applications, Inc. We have permanently moved two of our key employees to location at Rock Springs. We anticipate permanently relocating two more employees within the next quarter. Our mobile field office is in the process of being situated on site. We are awaiting Bureau of Land Management approval for electrical power installation to our site which also paces installation of telephones. A mobile phone is being installed to facilitate communications. A road has been cut providing access to Section 17 and a concrete pad cast for the foundation of our warehouse which will be erected upon rezoning approval tentatively expected November 18, 1977. Application has been made to the Department of Environmental Quality for installation of septic tank facilities on site which should be approved no later than November 30 .. 1977."