UNDERGROUND GASIFICATION FOR STEEPLY DIPPING COAL BEDS QUARTERLY PROGRESS REPORT FOR THE PERIOD JANUARY 1, 1981-MARCH 31, 1981

License(s):

Other (Open)

The detailed design of the Rawlins test no. 2 facility is complete. A bidder's conference was held at Rawlins for prospective general contractors for site construction. All long lead items have been identified and purchase orders have been issued. Spring drilling commenced this quarter and T-1 cavity studies were completed. Design modifications are complete for the product gas analysis trailer and the data acquisition system.

Followers: 0

Citation (Click to Copy)

Data and Resources

    Gathering Resources...

Keywords

Additional Info

Field Value
Last Updated September 29, 2016, 20:14 (LMT)
Created September 29, 2016, 20:14 (LMT)
Citation Roy Long, UNDERGROUND GASIFICATION FOR STEEPLY DIPPING COAL BEDS QUARTERLY PROGRESS REPORT FOR THE PERIOD JANUARY 1, 1981-MARCH 31, 1981, 2016-09-29, https://edx.netl.doe.gov/dataset/underground-gasification-for-steeply-dipping-coal-beds-quarterly-progress-report-for-the-period-jan
Netl Product yes
Poc Email Roy.long@netl.doe.gov
Point Of Contact Roy Long
Program Or Project KMD
Publication Date 1981-7-1